Closeout procedures

In closing out the project delivery process, what is the most likely claim if the architect does not prepare a final change order to adjust the contract sum when the cost of the work is more or less than the specified allowance?

Architect-Contractor roles

Which of the following statements about architect-contractor relationships is true? A. contractor-led design-build delivery method is not usually covered by most professional insurance policies, B. joint venture design-build delivery method is always covered by standard professional insurance policies, C. the design-builder is the architect's client in a contractor-led design-build arrangement, D. in joint venture design-build, the architect controls the development of the initial cost proposal and total project cost.

Good, fast and/or cheap

You are an owner with several projects already completed with the same contractor, including a single-story pediatric dentistry practice, a four-story public health dentistry center, and two-stories of oral & maxillofacial surgery suites. You seek to construct a new periodontal clinic building. You wish to build it good (quality), and cheap (minimal expense). Which of the following delivery methods is most suitable for you as an owner? A. fast-track B. design-build C. bridging D. multiple-prime E. design-bid-build

Overlapping services

Which of the following delivery processes permits the architect's design services to overlap construction activities, intended to result in expedited occupancy by the owner? A. design-bid-build B. design-build C. fast-track D. bridging documents Answer C. fast-track is a process that produces this. ARE 4.0 exam prep: PPP

Forms: G704/DB

The form G704/DB "Acknowledgement of Substantial Completion" is used on design-build projects and is similar to the traditional G704 "Certificate of Substantial Completion". However, only the owner & design-builder signs this form. Why has the space for architect's signature dropped in this form? Answer To eliminate a potential ethical conflict when the architect is a subcontractor to the design-builder, ensuring the architect is not pressured to sign off on a date that might trigger an early completion bonus or limit liquidated damages for late completion. ARE 4.0 exam prep: CDS

Work estimating

When allocating work by project phases, which of the following is a typical estimate breakdown into Schematic Design, Design Development, Construction Documents, Bidding&Negotiation, Contract Administration A. SD 10%, DD 10%, CD 50%, BN 10%, CA 20% B. SD 15%, DD 20%, CD 40%, BN 5%, CA 20% C. SD 5%, DD 30%, CD 30%, BD 5%, CA 30% D. SD 10%, DD 20%, CD 35%, BD 15%, CA 20% Answer B. SD 15%, DD 20%, CD 40%, BN 5%, CA 20% is a typical allocation. ARE 4.0 exam prep: PPP

Bridging documents delivery

What is the difference between DGIs and CDs in the bridging method of project delivery? Answer Design Guide Illustrations are prepared by the owner's design consultant and are a component of the Bridging Contract Documents. Contract Documents are final working dwgs prepared by the contractor's AE team. ARE 4.0 exam prep: PPP

CM@R

In Construction Manager at Risk delivery method, a cost guarantee or GMP is always provided. True or False? Answer False. @ Risk refers to the CM holding the trade contracts and taking on the financial obligation for construction. GMP is frequently, but not always, specified in the cost agreement.

Delivery methods

What delivery method is defined by the following three characteristics? 1. three prime players: owner, architect, ______ 2. two separate contracts: owner-architect, owner-_______ 3. final provider selection based on other features, but NOT cost Use of GMP is typical of this method, but when to set GMP is flexible and varies by project. Answer CM@R: Construction Manager At Risk. See PPP tab for link to AIA Best Practices Articles regarding delivery methods & compensation: BDCS

Fast-track delivery method

What type of contracting arrangement is commonly used to facilitate fast-track construction projects? Answer Many prime contracts allows one portion of the work to start before other elements are completely designed, but greatly increases the difficulty of project and contract coordination.