In a small office building (20,000sf), what is a reasonable breakdown of mechanical and electrical systems by percentage of total budget (projected cost = $2.5 million)? A. mech 10% / elec 5% B. mech 15% / elec 10% C. mech 20% / elec 10% D. mech 10% / elec 10% Answer D. mech 10% / elec 10%. A typical small office building project allocates equal percentages on mechanical and electrical systems for a total of 20% of the projected costs. ARE 4.0 exam prep: BS