Closeout procedures

In closing out the project delivery process, what is the most likely claim if the architect does not prepare a final change order to adjust the contract sum when the cost of the work is more or less than the specified allowance?



Answer: A claim may contend that the final application for payment has been improperly certified by the architect.
are-review.blogspot.com

Comments

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Fire evacuation

Which of the following statements best describes why exterior fire escapes are no longer recommended or usually permitted? A. Manufacturing has ceased production of these. B. Rising smoke from lower floors eliminates the safety of using them C. They cannot be securely attached to typical current construction D. They are difficult to maintain Answer B. is the correct answer. Smoke inhalation is as perilous as leaping flames. ARE 4.0 exam prep: BS

Tensegrity

A type of structure whose integrity is derived from the balance between members in tension and in compression is Tensegrity . Compressive components connected by tensile components to other compressive components form a tensegrity structure. What architect-engineer-cosmologist coined this term? Answer