What delivery method is defined by the following three characteristics?
1. three prime players: owner, architect, ______
2. two separate contracts: owner-architect, owner-_______
3. final provider selection based on other features, but NOT cost
Use of GMP is typical of this method, but when to set GMP is flexible and varies by project.

AnswerCM@R: Construction Manager At Risk.
See PPP tab for link to AIA Best Practices Articles regarding delivery methods & compensation: BDCS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Zoning terminology

What is the term for the maximum three-dimensional space on a zoning lot within which a structure can be built, as allowed by applicable height, setback and yard controls? Answer Zoning envelope or building envelope.