Delivery methods

What delivery method is defined by the following three characteristics?
1. three prime players: owner, architect, ______
2. two separate contracts: owner-architect, owner-_______
3. final provider selection based on other features, but NOT cost
Use of GMP is typical of this method, but when to set GMP is flexible and varies by project.

AnswerCM@R: Construction Manager At Risk.
See PPP tab for link to AIA Best Practices Articles regarding delivery methods & compensation: BDCS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD