What delivery method is defined by the following three characteristics?
1. three prime players: owner, architect, ______
2. two separate contracts: owner-architect, owner-_______
3. final provider selection based on other features, but NOT cost
Use of GMP is typical of this method, but when to set GMP is flexible and varies by project.

AnswerCM@R: Construction Manager At Risk.
See PPP tab for link to AIA Best Practices Articles regarding delivery methods & compensation: BDCS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Vapor retarders

In this section, a ceiling assembly separates the attic space above from the room interior below. If the building is located in Lewisville, Texas (hot-humid zone), where is the predicted location of condensation and what is the predicted condition of the gypsum board in this assembly? (Select 2 from the following) A. outside face of vapor retarder B. inside face of vapor retarder C. gypsum board will be wet D. gypsum board will be dry