Skip to main content

Good, fast and/or cheap

You are an owner with several projects already completed with the same contractor, including a single-story pediatric dentistry practice, a four-story public health dentistry center, and two-stories of oral & maxillofacial surgery suites. You seek to construct a new periodontal clinic building. You wish to build it good (quality), and cheap (minimal expense).

Which of the following delivery methods is most suitable for you as an owner?

A. fast-track
B. design-build
C. bridging
D. multiple-prime
E. design-bid-build




B. (correct) design-build is more likely to be good and cheap, but not necessarily fast.
A fast-track (A) speed that's good does not come cheap(ly). If you had no continuing A/E/C relationships, (C) might benefit you. (D) is used for a more complex, usually public agency project. (E) the most traditional form, may be good, not fast, and not necessarily cheapest.

are-review.blogspot.com

Comments

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Fire evacuation

Which of the following statements best describes why exterior fire escapes are no longer recommended or usually permitted? A. Manufacturing has ceased production of these. B. Rising smoke from lower floors eliminates the safety of using them C. They cannot be securely attached to typical current construction D. They are difficult to maintain Answer B. is the correct answer. Smoke inhalation is as perilous as leaping flames. ARE 4.0 exam prep: BS

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP