When allocating work by project phases, which of the following is a typical estimate breakdown into
Schematic Design, Design Development, Construction Documents, Bidding&Negotiation, Contract Administration
A. SD 10%, DD 10%, CD 50%, BN 10%, CA 20%
B. SD 15%, DD 20%, CD 40%, BN 5%, CA 20%
C. SD 5%, DD 30%, CD 30%, BD 5%, CA 30%
D. SD 10%, DD 20%, CD 35%, BD 15%, CA 20%
AnswerB. SD 15%, DD 20%, CD 40%, BN 5%, CA 20% is a typical allocation.