When allocating work by project phases, which of the following is a typical estimate breakdown into
Schematic Design, Design Development, Construction Documents, Bidding&Negotiation, Contract Administration

A. SD 10%, DD 10%, CD 50%, BN 10%, CA 20%
B. SD 15%, DD 20%, CD 40%, BN 5%, CA 20%
C. SD 5%, DD 30%, CD 30%, BD 5%, CA 30%
D. SD 10%, DD 20%, CD 35%, BD 15%, CA 20%

AnswerB. SD 15%, DD 20%, CD 40%, BN 5%, CA 20% is a typical allocation.

ARE 4.0 exam prep: PPP

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Zoning terminology

What is the term for the maximum three-dimensional space on a zoning lot within which a structure can be built, as allowed by applicable height, setback and yard controls? Answer Zoning envelope or building envelope.