Environmental impacts

Four steps in a process of evaluating a material or product to be used in a building:
1. Establish the intent and scope of the study 2. Conduct an inventory analysis 3. Carry out an impact assessment 4. Run an improvement analysis and summarize the study results
This describes:
A. Life-cycle cost analysis
B. Environmental impact statement
C. Life-cycle assessment
D. IEQ survey

AnswerC. Life-cycle assessment or LCA

ARE 4.0 exam prep: SPD

Comments

Try These Too!

Wood stairs

In wood stair construction, what is the difference between a carriage and a stringer?! Answer A carriage is the principle support for the treads and risers, whereas the stringer is the finish member (face) that treads and risers terminate against. ARE 4.0 exam prep: BDCS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS