Verbal change orders

All 5 requirements that must be satisfied for a valid oral modification to the contract:
1.
2.
3.
4.
5.
Answer1. + work can't have been included in the contract
2. owner ordered the extra work
3. owner had to agree to pay extra
4. contractor didn't voluntarily do the extra work
5. extra work can't be the contractor's own fault.


ARE 4.0 exam prep: CDS

Comments

  1. I didn't realize that an oral modification to the contract was possible. I'll go back to scan the documents now.

    ReplyDelete
  2. Aspects of verbal change orders is discussed in the 3/16 Schiff-Hardin Lecture. I got this highly recommended link thru ARE forum, an entire course audio record with notes (taught by a Chicago construction lawyer) is available here: http://www.schiffhardin.com/design-build/architecture544_Spring2010.htm

    ReplyDelete
  3. I assume the professor is using the 2007 AIA documents?

    ReplyDelete
  4. Yes, and the link to the lectures has been updated: http://www.schiffhardin.com/design-build/lecture-notes/architecture-544---spring-2011

    ReplyDelete

Post a Comment

Try These Too!

AIA Code of Ethics & Professional Conduct

The Code consists of three tiers of statements. Match them with an intent: I   Canon II  Ethical Standard III Rule of Conduct a: specific goals, which Members should strive to meet in professional performance b: mandatory, a violation of which is grounds for disciplinary action by the AIA c: broad principles of conduct Answer Ic, IIa, IIIb ARE 4.0 exam prep: PPP

Zoning terminology

What is the term for the maximum three-dimensional space on a zoning lot within which a structure can be built, as allowed by applicable height, setback and yard controls? Answer Zoning envelope or building envelope.

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%