Verbal change orders

All 5 requirements that must be satisfied for a valid oral modification to the contract:
1.
2.
3.
4.
5.
Answer1. + work can't have been included in the contract
2. owner ordered the extra work
3. owner had to agree to pay extra
4. contractor didn't voluntarily do the extra work
5. extra work can't be the contractor's own fault.


ARE 4.0 exam prep: CDS

Comments

  1. I didn't realize that an oral modification to the contract was possible. I'll go back to scan the documents now.

    ReplyDelete
  2. Aspects of verbal change orders is discussed in the 3/16 Schiff-Hardin Lecture. I got this highly recommended link thru ARE forum, an entire course audio record with notes (taught by a Chicago construction lawyer) is available here: http://www.schiffhardin.com/design-build/architecture544_Spring2010.htm

    ReplyDelete
  3. I assume the professor is using the 2007 AIA documents?

    ReplyDelete
  4. Yes, and the link to the lectures has been updated: http://www.schiffhardin.com/design-build/lecture-notes/architecture-544---spring-2011

    ReplyDelete

Post a Comment

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP