Skip to main content

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors:
Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%


Answer: Gross building area (GSF) = 15,000 sf. Either factor can be used to find the answer - 10,000 x 1.5 = 15,000sf or 10,000 / 0.66667 = 15,000sf (+/-)
are-review.blogspot.com

Comments

  1. question about this...the answer to this question is the gross area, but the question seemed like it was asking something else. also, it looks like the space factor wasn't needed to answer this question. why?

    ReplyDelete
  2. Like many potential exam questions, the wording of this one includes superfluous information that is unnecessary to finding the answer. The question asks to find the gross building area from the usable area of the classrooms.

    ReplyDelete
  3. The calcs in the answer are incorrect. Using the Building Efficiency Ratio to calculate the Gross Sq Ft you have to divide 10,000 by .67 not multiply.

    ReplyDelete
  4. Thanks Joshua! I just updated the answer notation.

    ReplyDelete
  5. I really appreciate the site, I find the example questions very useful in reviewing for the ARE tests, when the answer is viewable.

    Is it just me, or when you hover over the Answer is some of the answer cut off or sometimes shows up blank all together?

    Let me know if there is something I should be doing differently...thanks!

    ReplyDelete
    Replies
    1. Hi Jason, very glad the site is useful to you. Some browsers don't seem to show the answers all the time. Try Firefox, Chrome, or Safari. Internet Explorer works if it's IE9 or later. Thanks for visiting!

      Delete

Post a Comment

Try These Too!

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Fire-alarm & detection systems

In an atrium connecting 2 or more stories, what device types are generally required per section 907.2.13 of the International Fire Code (IFC)? Answer Fire alarm activated by automatic alarm, fire flow or manual alarm. Further, in Group A, E or M occupancies, emergency voice / alarm communication system is required per 907.2.12.2 (High-rise buildings). ARE 4.0 exam prep: BS

Model contract language

An owner-architect contract has stipulated an adjustment in compensation for reviewing re-submittals beyond a specified number. Where is this corresponding model language exist in order to coordinate with the contractor's responsibilities? 0.00.00 The Architect's review of Contractor's submittals will be limited to examination of an initial submittal and ____________ (_____) resubmittals. The Owner is entitled to obtain reimbursement from the Contractor for amounts paid to the Architect for evaluation of additional resubmittals. Answer It does not exist in the standard A201 general conditions of the contract for construction, and is recommended to be added to Section 3.12, as 3.12.11. ARE 4.0 exam study: CDS