Skip to main content

Verbal change orders

All 5 requirements that must be satisfied for a valid oral modification to the contract:
1.
2.
3.
4.
5.
Answer1. + work can't have been included in the contract
2. owner ordered the extra work
3. owner had to agree to pay extra
4. contractor didn't voluntarily do the extra work
5. extra work can't be the contractor's own fault.


ARE 4.0 exam prep: CDS

Comments

  1. I didn't realize that an oral modification to the contract was possible. I'll go back to scan the documents now.

    ReplyDelete
  2. Aspects of verbal change orders is discussed in the 3/16 Schiff-Hardin Lecture. I got this highly recommended link thru ARE forum, an entire course audio record with notes (taught by a Chicago construction lawyer) is available here: http://www.schiffhardin.com/design-build/architecture544_Spring2010.htm

    ReplyDelete
  3. I assume the professor is using the 2007 AIA documents?

    ReplyDelete
  4. Yes, and the link to the lectures has been updated: http://www.schiffhardin.com/design-build/lecture-notes/architecture-544---spring-2011

    ReplyDelete

Post a Comment

Try These Too!

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Water supply & demand

EPA.gov Domestic water consumption of an average american family of four is about how many gallons per day? A. 250, B. 400, C. 500, D. 650