Skip to main content

Verbal change orders

All 5 requirements that must be satisfied for a valid oral modification to the contract:
1.
2.
3.
4.
5.
Answer1. + work can't have been included in the contract
2. owner ordered the extra work
3. owner had to agree to pay extra
4. contractor didn't voluntarily do the extra work
5. extra work can't be the contractor's own fault.


ARE 4.0 exam prep: CDS

Comments

  1. I didn't realize that an oral modification to the contract was possible. I'll go back to scan the documents now.

    ReplyDelete
  2. Aspects of verbal change orders is discussed in the 3/16 Schiff-Hardin Lecture. I got this highly recommended link thru ARE forum, an entire course audio record with notes (taught by a Chicago construction lawyer) is available here: http://www.schiffhardin.com/design-build/architecture544_Spring2010.htm

    ReplyDelete
  3. I assume the professor is using the 2007 AIA documents?

    ReplyDelete
  4. Yes, and the link to the lectures has been updated: http://www.schiffhardin.com/design-build/lecture-notes/architecture-544---spring-2011

    ReplyDelete

Post a Comment

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.