Skip to main content

Verbal change orders

All 5 requirements that must be satisfied for a valid oral modification to the contract:
1.
2.
3.
4.
5.
Answer1. + work can't have been included in the contract
2. owner ordered the extra work
3. owner had to agree to pay extra
4. contractor didn't voluntarily do the extra work
5. extra work can't be the contractor's own fault.


ARE 4.0 exam prep: CDS

Comments

  1. I didn't realize that an oral modification to the contract was possible. I'll go back to scan the documents now.

    ReplyDelete
  2. Aspects of verbal change orders is discussed in the 3/16 Schiff-Hardin Lecture. I got this highly recommended link thru ARE forum, an entire course audio record with notes (taught by a Chicago construction lawyer) is available here: http://www.schiffhardin.com/design-build/architecture544_Spring2010.htm

    ReplyDelete
  3. I assume the professor is using the 2007 AIA documents?

    ReplyDelete
  4. Yes, and the link to the lectures has been updated: http://www.schiffhardin.com/design-build/lecture-notes/architecture-544---spring-2011

    ReplyDelete

Post a Comment

Try These Too!

Fire-alarm & detection systems

In an atrium connecting 2 or more stories, what device types are generally required per section 907.2.13 of the International Fire Code (IFC)? Answer Fire alarm activated by automatic alarm, fire flow or manual alarm. Further, in Group A, E or M occupancies, emergency voice / alarm communication system is required per 907.2.12.2 (High-rise buildings). ARE 4.0 exam prep: BS

Model contract language

An owner-architect contract has stipulated an adjustment in compensation for reviewing re-submittals beyond a specified number. Where is this corresponding model language exist in order to coordinate with the contractor's responsibilities? 0.00.00 The Architect's review of Contractor's submittals will be limited to examination of an initial submittal and ____________ (_____) resubmittals. The Owner is entitled to obtain reimbursement from the Contractor for amounts paid to the Architect for evaluation of additional resubmittals. Answer It does not exist in the standard A201 general conditions of the contract for construction, and is recommended to be added to Section 3.12, as 3.12.11. ARE 4.0 exam study: CDS

Plywood double-post!

Why are the plies in plywood turned at right angles in each successive layer? Answer This helps plywood panels to have a high degree of resistance to splitting. In this image, the panel consists of 3 plies. What is the name of each ply? Answer Face+Core+Face. In 5 or 7 ply panels, the core is sandwiched by crossbacks with a face and a back ply. ARE 4.0 exam prep: BDCS