Skip to main content

Verbal change orders

All 5 requirements that must be satisfied for a valid oral modification to the contract:
1.
2.
3.
4.
5.
Answer1. + work can't have been included in the contract
2. owner ordered the extra work
3. owner had to agree to pay extra
4. contractor didn't voluntarily do the extra work
5. extra work can't be the contractor's own fault.


ARE 4.0 exam prep: CDS

Comments

  1. I didn't realize that an oral modification to the contract was possible. I'll go back to scan the documents now.

    ReplyDelete
  2. Aspects of verbal change orders is discussed in the 3/16 Schiff-Hardin Lecture. I got this highly recommended link thru ARE forum, an entire course audio record with notes (taught by a Chicago construction lawyer) is available here: http://www.schiffhardin.com/design-build/architecture544_Spring2010.htm

    ReplyDelete
  3. I assume the professor is using the 2007 AIA documents?

    ReplyDelete
  4. Yes, and the link to the lectures has been updated: http://www.schiffhardin.com/design-build/lecture-notes/architecture-544---spring-2011

    ReplyDelete

Post a Comment

Try These Too!

Townships double post!

How many sections are contained within a township? Answer 36 (each is 1 mile square) What are the dimensions of 1/2 of a township? H & W Answer 18 miles square (3x6 sections) ARE 4.0 exam prep: SPD

Parking units

What are the car stall dimensions for a compact car? Answer A compact car stall size can be set by each municipality and therefore varies. Generally it is 7ft 6in wide by 15ft 0in long. However, in Fresno CA it's 8 1/2ft x 16ft and according to an Iowa urban design manual, it's 7ft 6in by 16ft. ARE 4.0 exam prep: SPD

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%