Skip to main content

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence?
AnswerNeither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote.

ARE 4.0 exam prep: CDS

Comments

  1. in this case, the GC would make the claim if any discrepancy right? there is no other way around it?

    ReplyDelete
  2. There are a number of ways to resolve discrepancies between specs & dwgs, which do happen. The AIA provides some guidance here: http://info.aia.org/knowledgebase/Discrepancies_between_drawings_and_specifications.htm (see A503 section 1.2.1). A claim would be brought when a cost difference is the issue, but it certainly isn't the first remedy desired by any party, when a clarification can be sought by the GC and the Architect can provide one. The contractor has a duty to report errors discovered during review of contract docs and field conditions per A201 to the attention of the Architect. Inconsistencies don't automatically mean cost increase to the work. Likewise, there is not an established hierarchy governing discrepancies between drawings and specs.

    ReplyDelete

Post a Comment

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Fire evacuation

Which of the following statements best describes why exterior fire escapes are no longer recommended or usually permitted? A. Manufacturing has ceased production of these. B. Rising smoke from lower floors eliminates the safety of using them C. They cannot be securely attached to typical current construction D. They are difficult to maintain Answer B. is the correct answer. Smoke inhalation is as perilous as leaping flames. ARE 4.0 exam prep: BS

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP