Skip to main content

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence?
AnswerNeither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote.

ARE 4.0 exam prep: CDS

Comments

  1. in this case, the GC would make the claim if any discrepancy right? there is no other way around it?

    ReplyDelete
  2. There are a number of ways to resolve discrepancies between specs & dwgs, which do happen. The AIA provides some guidance here: http://info.aia.org/knowledgebase/Discrepancies_between_drawings_and_specifications.htm (see A503 section 1.2.1). A claim would be brought when a cost difference is the issue, but it certainly isn't the first remedy desired by any party, when a clarification can be sought by the GC and the Architect can provide one. The contractor has a duty to report errors discovered during review of contract docs and field conditions per A201 to the attention of the Architect. Inconsistencies don't automatically mean cost increase to the work. Likewise, there is not an established hierarchy governing discrepancies between drawings and specs.

    ReplyDelete

Post a Comment

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.