Risk management

How does an owner provide a financial safeguard for the following situations:
- unanticipated price escalation of a particular product
- an architect’s omission of flashing in the construction documents
- a necessary change during construction, modifying the project’s scope.
A. Allowance
B. Alternates
C. Contingency
D. Escalation

AnswerC. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents.

ARE 4.0 exam prep: PPP

Comments

Try These Too!

C&D Debris

Which of the following materials are typically excluded from a state's legal definition of construction and demolition debris? Choose 3 A. Non-asbestos insulation, B. Asbestos tile, C. Roofing cement, D. Framing lumber E. Asphalt shingles, F. Drywall, G. Treated wood ties

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°