In case there is a discrepancy between specifications and the drawings, which takes precedence?
AnswerNeither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote.

ARE 4.0 exam prep: CDS

Comments

  1. in this case, the GC would make the claim if any discrepancy right? there is no other way around it?

    ReplyDelete
  2. There are a number of ways to resolve discrepancies between specs & dwgs, which do happen. The AIA provides some guidance here: http://info.aia.org/knowledgebase/Discrepancies_between_drawings_and_specifications.htm (see A503 section 1.2.1). A claim would be brought when a cost difference is the issue, but it certainly isn't the first remedy desired by any party, when a clarification can be sought by the GC and the Architect can provide one. The contractor has a duty to report errors discovered during review of contract docs and field conditions per A201 to the attention of the Architect. Inconsistencies don't automatically mean cost increase to the work. Likewise, there is not an established hierarchy governing discrepancies between drawings and specs.

    ReplyDelete

Post a Comment

Try These Too!

Elevator bank layouts

An office building has an elevator bank with 4 elevators where 2 cabs side-by-side are arranged opposite the other 2. Each of the elevators is 3500-pound capacity with an interior cab dimension of 6'8" x 5'4". What is the recommended corridor width at this group? A. 8 feet B. 9 feet C. 11 feet D. 12 feet Answer C. 11 feet. At 1.5-2 times the car depth (5'4), this could be a range, but 10 feet is a minimum for groups of 4 or more. Therefore C is the best choice. ARE 4.0 exam prep: BDCS

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Floor receptacles

To qualify as one of the required power receptacles in a dwelling, according to NEC, what is the maximum distance from the wall that this recessed or surface-mounted floor receptacle close to an exterior wall may be? Answer Less than or equal to 18 inches. Additional requirements apply, such as approved floor box housing, cover... ARE 4.0 exam prep: BS