Addenda must be issued no less than 4 days prior to the date that Bids are due, allowing the Bidders the opportunity to incorporate changes to their bids. What are the two exceptions - when can an addendum be issued less than 4 days prior to the date of receipt of Bids?

AnswerExceptions: 1. an addendum withdrawing the request for Bids. 2. an addendum that includes the postponement of the date for receipt of Bids.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP