Claims

Which document outlines the procedure for making a claim or handling a dispute?
A. B101-2007 Standard Form of Agreement between Owner & Architect
B. A201-2007 General Conditions of the Contract for Construction
C. A503-2007 Guide for Supplementary Conditions
D. A103-2007 Standard Form of Agreement between Owner & Contractor


Answer is B. A201-2007 The General Conditions of the Contract for Construction.
are-review.blogspot.com

Comments

Try These Too!

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP

Mold

Mold is one of the potential contributors to poor indoor air quality and it requires 1. moisture, 2. a nutrient and 3. a particular temperature range. What temperature range supports its growth and which requirement is key to controlling its growth? Answer 40deg - 100deg F (4deg - 38deg C). Thus moisture control is the only way to prevent mold in buildings. ARE 4.0 exam study: BS