How can the Architect be compensated if the Owner continues to use the Architect's Instruments of Service in order to complete the project after the Architect agreement has been terminated (either at the Owner's convenience or by the Architect)?




Answer: By paying a licensing fee to the Architect as compensation as stipulated in 11.9 of the AIA B101 agreement.

For more exam resources also check out these pages CE and PcM-PjM 

Comments

Try These Too!

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°