Skip to main content

Instruments of service

How can the Architect be compensated if the Owner continues to use the Architect's Instruments of Service in order to complete the project after the Architect agreement has been terminated (either at the Owner's convenience or by the Architect)?




Answer: By paying a licensing fee to the Architect as compensation as stipulated in 11.9 of the AIA B101 agreement.