How can the Architect be compensated if the Owner continues to use the Architect's Instruments of Service in order to complete the project after the Architect agreement has been terminated (either at the Owner's convenience or by the Architect)?




Answer: By paying a licensing fee to the Architect as compensation as stipulated in 11.9 of the AIA B101 agreement.

For more exam resources also check out these pages CE and PcM-PjM 

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.