Skip to main content

Instruments of service

How can the Architect be compensated if the Owner continues to use the Architect's Instruments of Service in order to complete the project after the Architect agreement has been terminated (either at the Owner's convenience or by the Architect)?




Answer: By paying a licensing fee to the Architect as compensation as stipulated in 11.9 of the AIA B101 agreement.

For more exam resources also check out these pages CE and PcM-PjM 

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS

Collector walks

Walks next to parking areas where vehicles are able to overhang the walk should be a minimum width. What is this minimum in feet? A. 3 feet B. 4 feet C. 5 feet D. 6 feet Answer These walks should be 6 ft (D.) minimum in width. ARE 4.0 exam prep: SPD