Bid Validity

Why may an owner reject, or consider "unresponsive", a bid that proposes more than the requirements in the documents?



Answer:  To be valid, a bid must conform to the requirements of the advertisement, invitation to bid and instructions to bidders.

Visit the Construction and Evaluation page for more study resources

Comments

Try These Too!

AIA Code of Ethics & Professional Conduct

The Code consists of three tiers of statements. Match them with an intent: I   Canon II  Ethical Standard III Rule of Conduct a: specific goals, which Members should strive to meet in professional performance b: mandatory, a violation of which is grounds for disciplinary action by the AIA c: broad principles of conduct Answer Ic, IIa, IIIb ARE 4.0 exam prep: PPP

Zoning terminology

What is the term for the maximum three-dimensional space on a zoning lot within which a structure can be built, as allowed by applicable height, setback and yard controls? Answer Zoning envelope or building envelope.

Structural Tee

Two types of structural tee shapes are "WT" and "ST" shapes. How are these two different shapes derived? Answer WTs are cut from wide-flange sections (W shapes). STs are cut from American Standard I-beams (S shapes). ARE 4.0 exam prep: SS