Bid Validity

Why may an owner reject, or consider "unresponsive", a bid that proposes more than the requirements in the documents?



Answer:  To be valid, a bid must conform to the requirements of the advertisement, invitation to bid and instructions to bidders.

Visit the Construction and Evaluation page for more study resources

Comments

Try These Too!

Space programming

What are two common ways to identify and document physical and functional relationships amongst spaces in the programing phase? Choose 2 A. adjacency diagram B. adjacency matrix C. bubble diagramming D. block-stack diagram Answer A & B The adjacency diagram and adjacency matrix are used in programming stage, while C & D are employed as the initial design effort begins as more physical representations of plan are introduced. ARE 4.0 exam prep: PPP

Overimprovement

While underimprovement describes property that is not being put to its highest and best use (reducing its value), when does overimprovement apply?

Vapor retarders

In this section, a ceiling assembly separates the attic space above from the room interior below. If the building is located in Lewisville, Texas (hot-humid zone), where is the predicted location of condensation and what is the predicted condition of the gypsum board in this assembly? (Select 2 from the following) A. outside face of vapor retarder B. inside face of vapor retarder C. gypsum board will be wet D. gypsum board will be dry