Skip to main content

Lighting selection

In a materials reference showroom, an area of study carrels is set aside for industry professionals to review product literature and reference materials. The showroom's reference center is open from 7 am through 10 pm every day and the owners of the center would like to reduce the energy consumption and expense. Which of the following is the best choice of lighting selection for this portion of the center.
A. ambient lighting
B. general illumination
C. task lighting
D. accent lighting



Answer is C. task lighting would permit energy conservation as light at unused carrels can be turned off or lowered.

are-review PPD-PDD resources

Comments

Try These Too!

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Model contract language

An owner-architect contract has stipulated an adjustment in compensation for reviewing re-submittals beyond a specified number. Where is this corresponding model language exist in order to coordinate with the contractor's responsibilities? 0.00.00 The Architect's review of Contractor's submittals will be limited to examination of an initial submittal and ____________ (_____) resubmittals. The Owner is entitled to obtain reimbursement from the Contractor for amounts paid to the Architect for evaluation of additional resubmittals. Answer It does not exist in the standard A201 general conditions of the contract for construction, and is recommended to be added to Section 3.12, as 3.12.11. ARE 4.0 exam study: CDS

Fire-alarm & detection systems

In an atrium connecting 2 or more stories, what device types are generally required per section 907.2.13 of the International Fire Code (IFC)? Answer Fire alarm activated by automatic alarm, fire flow or manual alarm. Further, in Group A, E or M occupancies, emergency voice / alarm communication system is required per 907.2.12.2 (High-rise buildings). ARE 4.0 exam prep: BS