Punch List!

The Contractor does NOT perform an inspection of the work after the punch list is complete. Why?


The Architect inspects for completeness to determine if the job is substantially complete.
are-review.blogspot.com

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.