Contract Terms and Design Project Costs

Regardless of contract format (AIA standard or other), the contract language must provide clear description of all of the following included in the base fee except: (Select 2)
A. major project milestone dates, B. scope of services, C. reimbursable expenses with respective unit billing rate, D. multiple review of submittals, E. physical and virtual building models, F. number of meetings with third parties included (authorities having jurisdiction, landlords)


Answer is D and E items are not included in the base fee, but should be identified and described as additional services in the contract.
are-review.blogspot.com

Comments

Try These Too!

Calculate Luminance

A typical 60-watt standard frosted incandescent bulb outputs 890 lumens for an efficacy ratio of about 15 lumens per watt. As an A19, its shape is spherical. What is the its calculated luminance? A. 25,115 cd/in² B. 25.115 cd/ft² C. 25,115 cd/m² D. Indeterminate, missing variable. Answer If 1 candela (cd) = 4 ∏ lumens (lm), 890 x 1cd/4∏ = 71 cd, A19 = 19/8 = 2.375 in or 60mm diameter (= 30mm radius), L = intensity / projected area, 71 cd / ∏ r² = 71/ 3.14 x (.03m)² = 25,115 cd/m² ARE 4.0 exam prep: BS

Characteristics of form

Which example illustrates a regular ordering of elements producing RHYTHM? A B C D Answer Answer is C. A = proportion, B = symmetry, D = balance ARE 4.0 exam prep: PPP

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°