Regardless of contract format (AIA standard or other), the contract language must provide clear description of all of the following included in the base fee except: (Select 2)
A. major project milestone dates, B. scope of services, C. reimbursable expenses with respective unit billing rate, D. multiple review of submittals, E. physical and virtual building models, F. number of meetings with third parties included (authorities having jurisdiction, landlords)


Answer is D and E items are not included in the base fee, but should be identified and described as additional services in the contract.
are-review.blogspot.com

Comments

Try These Too!

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°