Contract Terms and Design Project Costs

Regardless of contract format (AIA standard or other), the contract language must provide clear description of all of the following included in the base fee except: (Select 2)
A. major project milestone dates, B. scope of services, C. reimbursable expenses with respective unit billing rate, D. multiple review of submittals, E. physical and virtual building models, F. number of meetings with third parties included (authorities having jurisdiction, landlords)


Answer is D and E items are not included in the base fee, but should be identified and described as additional services in the contract.
are-review.blogspot.com

Comments

Try These Too!

Wood stairs

In wood stair construction, what is the difference between a carriage and a stringer?! Answer A carriage is the principle support for the treads and risers, whereas the stringer is the finish member (face) that treads and risers terminate against. ARE 4.0 exam prep: BDCS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS