In coordinating the construction drawing set with the project specifications, the information provided in these two elements of the contract documents must NOT (choose 2)
A. correlate, B. duplicate, C. complement
D. overlap, E. coordinate, F. match


Answers B and D are correct.
The two documents should complement each other to form a complete set. Confusion and subsequently dispute with contractors arises from conflicting information, often the result of duplicated or overlapping content.
are-review.blogspot.com

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP