Document coordination

In coordinating the construction drawing set with the project specifications, the information provided in these two elements of the contract documents must NOT (choose 2)
A. correlate, B. duplicate, C. complement
D. overlap, E. coordinate, F. match


Answers B and D are correct.
The two documents should complement each other to form a complete set. Confusion and subsequently dispute with contractors arises from conflicting information, often the result of duplicated or overlapping content.
are-review.blogspot.com

Comments

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Fire evacuation

Which of the following statements best describes why exterior fire escapes are no longer recommended or usually permitted? A. Manufacturing has ceased production of these. B. Rising smoke from lower floors eliminates the safety of using them C. They cannot be securely attached to typical current construction D. They are difficult to maintain Answer B. is the correct answer. Smoke inhalation is as perilous as leaping flames. ARE 4.0 exam prep: BS

Tensegrity

A type of structure whose integrity is derived from the balance between members in tension and in compression is Tensegrity . Compressive components connected by tensile components to other compressive components form a tensegrity structure. What architect-engineer-cosmologist coined this term? Answer