Skip to main content

Document coordination

In coordinating the construction drawing set with the project specifications, the information provided in these two elements of the contract documents must NOT (choose 2)
A. correlate, B. duplicate, C. complement
D. overlap, E. coordinate, F. match


Answers B and D are correct.
The two documents should complement each other to form a complete set. Confusion and subsequently dispute with contractors arises from conflicting information, often the result of duplicated or overlapping content.
are-review.blogspot.com

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Required cooling capacity

Roughly 3 tons of cooling is being estimated for a 2,700 square foot residential building. Choose 2 locations in which this estimation can be applied. A. Rhode Island B. Ontario, Canada C. Nevada D. North Carolina Answer A and B are the best answers. As a rule of thumb, 1 ton will cool 800-1000 sf in the northern US and Canada, but only 450-700 sf in the southern US. Thus, 2700 sf divided by 900 sf per ton = 3 tons. ARE 4.0 exam prep: BS