An item that was not included on the contractor's punch list has been discovered to be incomplete after final inspection. Who is responsible for correcting the item?
A. Architect, B. Owner
C. Contractor, D. not determinable outside mediation


Answer is C. Contractor. According to A201 Section 9.8.3, the Contractor is responsible for correcting or completing the item upon notification by the Architect, after which another inspection by Architect is performed to determine Substantial Completion.
are-review.blogspot.com

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%