Close-out procedures

An item that was not included on the contractor's punch list has been discovered to be incomplete after final inspection. Who is responsible for correcting the item?
A. Architect, B. Owner
C. Contractor, D. not determinable outside mediation


Answer is C. Contractor. According to A201 Section 9.8.3, the Contractor is responsible for correcting or completing the item upon notification by the Architect, after which another inspection by Architect is performed to determine Substantial Completion.
are-review.blogspot.com

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.