Close-out procedures

An item that was not included on the contractor's punch list has been discovered to be incomplete after final inspection. Who is responsible for correcting the item?
A. Architect, B. Owner
C. Contractor, D. not determinable outside mediation


Answer is C. Contractor. According to A201 Section 9.8.3, the Contractor is responsible for correcting or completing the item upon notification by the Architect, after which another inspection by Architect is performed to determine Substantial Completion.
are-review.blogspot.com

Comments

Try These Too!

Wood stairs

In wood stair construction, what is the difference between a carriage and a stringer?! Answer A carriage is the principle support for the treads and risers, whereas the stringer is the finish member (face) that treads and risers terminate against. ARE 4.0 exam prep: BDCS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS