Systems costs

In a small office building (20,000sf), what is a reasonable breakdown of mechanical and electrical systems by percentage of total budget (projected cost = $2.5 million)?

A. mech 10% / elec 5%
B. mech 15% / elec 10%
C. mech 20% / elec 10%
D. mech 10% / elec 10%

AnswerD. mech 10% / elec 10%. A typical small office building project allocates equal percentages on mechanical and electrical systems for a total of 20% of the projected costs.
ARE 4.0 exam prep: BS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD