Skip to main content

System voltage

In this diagram, if the first load is a 120V computer, what is the second load shown?
A. single phase transformer, 480/120-240V
B. 208V 3-phase motor
C. 208V heater, single phase
D. 277V discharge fluorescent lighting

AnswerC. 208V heater, single phase. Neutral to any single panel bus = 120V. A load connecting two panel buses (not neutral) is 208V single phase; between three panel buses is 208V 3-phase. Since the computer is 120V, system voltage cannot be 277/480.
ARE 4.0 exam prep: BS

Comments

Try These Too!

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP

Mold

Mold is one of the potential contributors to poor indoor air quality and it requires 1. moisture, 2. a nutrient and 3. a particular temperature range. What temperature range supports its growth and which requirement is key to controlling its growth? Answer 40deg - 100deg F (4deg - 38deg C). Thus moisture control is the only way to prevent mold in buildings. ARE 4.0 exam study: BS