System voltage

In this diagram, if the first load is a 120V computer, what is the second load shown?
A. single phase transformer, 480/120-240V
B. 208V 3-phase motor
C. 208V heater, single phase
D. 277V discharge fluorescent lighting

AnswerC. 208V heater, single phase. Neutral to any single panel bus = 120V. A load connecting two panel buses (not neutral) is 208V single phase; between three panel buses is 208V 3-phase. Since the computer is 120V, system voltage cannot be 277/480.
ARE 4.0 exam prep: BS

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%