A field observation report should NOT record one of the following:
A. weather conditions on site
B. count or estimated count of workers present
C. estimated cost of corrections to be made
D. estimate of the conformance with work schedule
E. list of items to verify, information or action to be required
AnswerC. estimated cost of corrections to be made. Observations of work in progress should be described, but estimating the cost of work that must be corrected is neither required of the Architect nor a part of the field observation report.
ARE 4.0 exam prep: CDS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Deflection: steel or wood

For EITHER steel or wood beams, a question that asks for the allowable deflection limit (maximum) for live loads only requires which of the following equations? A. L/240 B. L/360 C. ∆ = 5wl⁴ / 384EI D. ∆ = 5Wl³ / 384EI Answer B. L/360 or span in inches divided by 360. ARE 4.0 exam prep: SS Note on calculations: From posted discussions on AREforum , memorization of most equations is not advised. However, even when the equation may be available in in-exam reference, selection of the appropriate equation requires correct identification.

Townships double post!

How many sections are contained within a township? Answer 36 (each is 1 mile square) What are the dimensions of 1/2 of a township? H & W Answer 18 miles square (3x6 sections) ARE 4.0 exam prep: SPD