Site observation

A field observation report should NOT record one of the following:
A. weather conditions on site
B. count or estimated count of workers present
C. estimated cost of corrections to be made
D. estimate of the conformance with work schedule
E. list of items to verify, information or action to be required
AnswerC. estimated cost of corrections to be made. Observations of work in progress should be described, but estimating the cost of work that must be corrected is neither required of the Architect nor a part of the field observation report.
ARE 4.0 exam prep: CDS

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors