Site observation

A field observation report should NOT record one of the following:
A. weather conditions on site
B. count or estimated count of workers present
C. estimated cost of corrections to be made
D. estimate of the conformance with work schedule
E. list of items to verify, information or action to be required
AnswerC. estimated cost of corrections to be made. Observations of work in progress should be described, but estimating the cost of work that must be corrected is neither required of the Architect nor a part of the field observation report.
ARE 4.0 exam prep: CDS

Comments

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Fire evacuation

Which of the following statements best describes why exterior fire escapes are no longer recommended or usually permitted? A. Manufacturing has ceased production of these. B. Rising smoke from lower floors eliminates the safety of using them C. They cannot be securely attached to typical current construction D. They are difficult to maintain Answer B. is the correct answer. Smoke inhalation is as perilous as leaping flames. ARE 4.0 exam prep: BS

Tensegrity

A type of structure whose integrity is derived from the balance between members in tension and in compression is Tensegrity . Compressive components connected by tensile components to other compressive components form a tensegrity structure. What architect-engineer-cosmologist coined this term? Answer