The project team including contractor meet regularly at a bi-weekly construction meeting. Which of the following is NOT an appropriate agenda item that could be discussed?
A. Occupancy-permit procedures
B. Status of change orders
C. Notification of future addenda
D. Pre-commissioning procedures

AnswerC. Notification of future addenda. Addenda are only issued before the bidding period has concluded. Changes made to the contract documents during construction will be change orders.
ARE 4.0 exam prep: CDS

Comments

Try These Too!

Overimprovement

While underimprovement describes property that is not being put to its highest and best use (reducing its value), when does overimprovement apply?

Change in services

An owner may authorize a change in services for which a written scope of duties is attached to the owner-architect contract, to provide a higher degree of monitoring or observing work on site than expected under basic construction phase services for architect's site visits. What is this role and when does it occur?

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS