Project meetings

The project team including contractor meet regularly at a bi-weekly construction meeting. Which of the following is NOT an appropriate agenda item that could be discussed?
A. Occupancy-permit procedures
B. Status of change orders
C. Notification of future addenda
D. Pre-commissioning procedures

AnswerC. Notification of future addenda. Addenda are only issued before the bidding period has concluded. Changes made to the contract documents during construction will be change orders.
ARE 4.0 exam prep: CDS

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.