Skip to main content

Fundamental period

Period (time needed to complete a seismic wave cycle) in seconds is given for each of the following: equipment (filing cabinet), one-story structure, 4 stories, 10-20 stories, 70 story skyscraper.
What is the primary determinant of a building's fundamental period?

AnswerBuilding height more than its structural system, materials or proportions determines its period. Rule of thumb: period = # stories / 10
ARE 4.0 exam prep: SS

Comments

Try These Too!

Wood stairs

In wood stair construction, what is the difference between a carriage and a stringer?! Answer A carriage is the principle support for the treads and risers, whereas the stringer is the finish member (face) that treads and risers terminate against. ARE 4.0 exam prep: BDCS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS