When would the following diagram be used?
A. to illustrate the initial results of spatial organization using an adjacency diagram as a basis
B. to illustrate the required adjacencies and priorities of relationships just prior to initial space planning
C. to represent relationships in a matrix of adjacencies
D. to indicate scheduling process

AnswerA. the block diagram illustrates the initial results of spatial organization using an adjacency diagram as a basis.

ARE 4.0 exam prep: PPP

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD