B101-2007 incorporates a public policy of the AIA that architects must be environmentally responsible in performing their services. As part of the architect's basic services, an architect is required to discuss during schematic design phase the feasibility of including environmentally responsible design approaches in the project. In reviewing environmentally responsible design alternatives, the client agrees that energy modeling should be performed. How is this type of service classified?

AnswerThis should be identified in Article 4 as an additional service (extensive environmentally responsible design) for which additional compensation is required.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD