Compensation

Why is the multiple of direct personnel expense method preferable when a client has no prior involvement or experience developing a project and has not yet settled on a program for it?
A. The client would achieve programming, a non-basic architectural service, without additional expense.
B. The architect would be compensated regardless of the additional time involved to deliver programming services.
C. This method promotes faster decision-making as the client will pay a fixed amount for a specific set of services.
D. This method is scaled to the cost of construction.

AnswerB is the best selection. Direct personnel expense is a variant of cost plus fee compensation and is primarily beneficial to the architect to cover its costs and profit.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Fire-alarm & detection systems

In an atrium connecting 2 or more stories, what device types are generally required per section 907.2.13 of the International Fire Code (IFC)? Answer Fire alarm activated by automatic alarm, fire flow or manual alarm. Further, in Group A, E or M occupancies, emergency voice / alarm communication system is required per 907.2.12.2 (High-rise buildings). ARE 4.0 exam prep: BS

Model contract language

An owner-architect contract has stipulated an adjustment in compensation for reviewing re-submittals beyond a specified number. Where is this corresponding model language exist in order to coordinate with the contractor's responsibilities? 0.00.00 The Architect's review of Contractor's submittals will be limited to examination of an initial submittal and ____________ (_____) resubmittals. The Owner is entitled to obtain reimbursement from the Contractor for amounts paid to the Architect for evaluation of additional resubmittals. Answer It does not exist in the standard A201 general conditions of the contract for construction, and is recommended to be added to Section 3.12, as 3.12.11. ARE 4.0 exam study: CDS