Boiler & Machinery Insurance

Boiler and machinery insurance purchased by the Owner for such equipment required by the Contract Documents covers the insured objects during installation and until which of the following?
A. until expiration of the period for correction of Work
B. until 30 days' prior written notice by the Contractor
C. until application of consent from the insurance company
D. until final acceptance by Owner

AnswerD. until final acceptance by Owner. Article 11 of A201 describes the various types of insurance that may be required. See 11.3.2 for Boiler and Machinery Insurance.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD