The Superintendent

New sections 3.9.2-3 in A201-2007 now provide the owner and architect with what new opportunity with regard to the contractor's superintendent?

AnswerThe contractor must furnish the owner & architect with the name + qualifications of a proposed superintendent for the project site, after which the architect has 14 days to object to or require more time to review. Also, the contractor can't change out the superintendent without the owners consent.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.