New sections 3.9.2-3 in A201-2007 now provide the owner and architect with what new opportunity with regard to the contractor's superintendent?

AnswerThe contractor must furnish the owner & architect with the name + qualifications of a proposed superintendent for the project site, after which the architect has 14 days to object to or require more time to review. Also, the contractor can't change out the superintendent without the owners consent.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP