The Superintendent

New sections 3.9.2-3 in A201-2007 now provide the owner and architect with what new opportunity with regard to the contractor's superintendent?

AnswerThe contractor must furnish the owner & architect with the name + qualifications of a proposed superintendent for the project site, after which the architect has 14 days to object to or require more time to review. Also, the contractor can't change out the superintendent without the owners consent.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%