New sections 3.9.2-3 in A201-2007 now provide the owner and architect with what new opportunity with regard to the contractor's superintendent?

AnswerThe contractor must furnish the owner & architect with the name + qualifications of a proposed superintendent for the project site, after which the architect has 14 days to object to or require more time to review. Also, the contractor can't change out the superintendent without the owners consent.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Structural forces

Choose a term that best identifies the type of force shown in this diagram - A. collinear B. concurrent C. nonconcurrent D. noncoplanar

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred