Submittal review duration

How is the duration of submittal review by the architect managed so that it is considered within reasonable promptness?
1. Per amount of time specified in the Owner-Architect Agreement.
2. Amount of time defined in the General Conditions of the Contract for Construction.
3. Allowable time as indicated by Architect in Division 1.
4. Per schedule of submittals included with contractor's construction schedule.
Answer
ARE 4.0 exam prep: CDS

Comments

Try These Too!

Fire-alarm & detection systems

In an atrium connecting 2 or more stories, what device types are generally required per section 907.2.13 of the International Fire Code (IFC)? Answer Fire alarm activated by automatic alarm, fire flow or manual alarm. Further, in Group A, E or M occupancies, emergency voice / alarm communication system is required per 907.2.12.2 (High-rise buildings). ARE 4.0 exam prep: BS

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Overimprovement

While underimprovement describes property that is not being put to its highest and best use (reducing its value), when does overimprovement apply?