Submittal review duration

How is the duration of submittal review by the architect managed so that it is considered within reasonable promptness?
1. Per amount of time specified in the Owner-Architect Agreement.
2. Amount of time defined in the General Conditions of the Contract for Construction.
3. Allowable time as indicated by Architect in Division 1.
4. Per schedule of submittals included with contractor's construction schedule.
Answer
ARE 4.0 exam prep: CDS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Footing cross-section

When the thickness of a foundation wall = 6", the cross-sectional proportions in this image are appropriate for which of the following: A. a footing supported on clay soil B. light frame construction supporting one floor and one roof C. allowable bearing capacity of foundation soil is low in relation to building loads D. when a continuous footing is required Answer B. light frame construction supporting one floor and one roof (in accordance with Table 1805.4.2) ARE 4.0 exam prep: PPP