What is the name of the test carried out to determine the optimum relationship between moisture content and fill density? The following steps proceed from the results:
1. Laboratory tests of fill samples determine the amount of compaction required before construction begins.
2. Fill is deposited on site in a series of compacted layers between 8-12 inches.
3. 95-100% compaction of optimum (tested) density of the site soil must be achieved.
Answer
1. Laboratory tests of fill samples determine the amount of compaction required before construction begins.
2. Fill is deposited on site in a series of compacted layers between 8-12 inches.
3. 95-100% compaction of optimum (tested) density of the site soil must be achieved.