Skip to main content

Soil testing

What is the name of the test carried out to determine the optimum relationship between moisture content and fill density? The following steps proceed from the results:
1. Laboratory tests of fill samples determine the amount of compaction required before construction begins.
2. Fill is deposited on site in a series of compacted layers between 8-12 inches.
3. 95-100% compaction of optimum (tested) density of the site soil must be achieved.
Answer

Comments

Try These Too!

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors