Multi-wythe masonry

Where hollow units make up a multi-wythe wall, bonded by masonry headers, if the stretcher courses are bonded at vertical intervals up to 34", units must lap the units below by at least ____ inches?
A. 1.5 inch
B. 2.5 inches
C. 3 inches
D. 3-5/8 inches
E. 4 inches
AnswerC. 3 inches

ARE 4.0 exam prep: BDCS

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP