A deductive change order (amount of work is reduced by change order) typically includes contractor overhead & profit. True or False?
AnswerFalse, the original bid would have included the contractor's time to line up subs and estimate costs. When combining + & - change orders the net difference would include overhead & profit.
ARE 4.0 exam prep: CDS
AnswerFalse, the original bid would have included the contractor's time to line up subs and estimate costs. When combining + & - change orders the net difference would include overhead & profit.
ARE 4.0 exam prep: CDS