Base bids

Base bids do not include:

A. bid price
B. bid bond
C. allowances
D. alternates


Answer: A. bid price is the amount of the bid, B. bid bond is a bid security to guarantee the successful bidder will enter into contract, D. alternates are not included. Included in base bid: C. allowances, amount can be adjusted later through change order.

For more CE exam resources see the CE page

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD