Base bids

Base bids do not include:

A. bid price
B. bid bond
C. allowances
D. alternates


Answer: A. bid price is the amount of the bid, B. bid bond is a bid security to guarantee the successful bidder will enter into contract, D. alternates are not included. Included in base bid: C. allowances, amount can be adjusted later through change order.

For more CE exam resources see the CE page

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Overimprovement

While underimprovement describes property that is not being put to its highest and best use (reducing its value), when does overimprovement apply?

Construction type

Fire-resistance rating requirements listed in IBC Table 601 list major building elements based on construction classification. Match these two criteria correctly, choose 2 A. Type IB = roof construction 1 1/2 hrs B. Type IIB = exterior bearing walls 1 hr C. Type IIIA = structural frame 1 hr D. Type VB = floor construction 1 hr E. Type IVHT = exterior bearing walls 2 hr Answer C. and E. are correct. HT = heavy timber. ARE 4.0 exam prep: BDCS Reference tip:  Find the online version of Table 601 in this discussion paper here