An owner may authorize a change in services for which a written scope of duties is attached to the owner-architect contract, to provide a higher degree of monitoring or observing work on site than expected under basic construction phase services for architect's site visits. What is this role and when does it occur?
What are two common ways to identify and document physical and functional relationships amongst spaces in the programing phase? Choose 2 A. adjacency diagram B. adjacency matrix C. bubble diagramming D. block-stack diagram Answer A & B The adjacency diagram and adjacency matrix are used in programming stage, while C & D are employed as the initial design effort begins as more physical representations of plan are introduced. ARE 4.0 exam prep: PPP