When planning installation of new services for a site, which of the following services are given priority over the others.
Gas
Water
Sanitary
Electric
Storm

Select:
I. Gas, Electric, Water
II. Water, Sanitary
III. Water
IV. Storm, Sanitary
IV. Gas, Water

AnswerIV. Storm and sanitary sewers require the flow of gravity to drain to municipal disposal systems or private treatment facilities.

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD