Utility considerations

When planning installation of new services for a site, which of the following services are given priority over the others.
Gas
Water
Sanitary
Electric
Storm

Select:
I. Gas, Electric, Water
II. Water, Sanitary
III. Water
IV. Storm, Sanitary
IV. Gas, Water

AnswerIV. Storm and sanitary sewers require the flow of gravity to drain to municipal disposal systems or private treatment facilities.

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Clear Floor Area

What is the clear floor area required for this front approach at an accessible water fountain? (yellow dash line) A. 36 x 60 B. 36 x 48 C. 30 x 48 D. 30 x 60 Answer C. 30 x 48. Although set in an alcove, the depth of the recess is not 24 inches or greater, which requires a 36 inch clear width. ARE 4.0 exam prep: SPD

Building setback

Which of the following determines building setback requirements (required minimum distances from property line to building)? A. deed restrictions B. building codes C. bulk plane covenant D. zoning regulations Answer D. zoning regulations ARE 4.0 exam prep: SPD