Shop drawing review




Shop drawing review stamps will typically state that the review does not include which of these:
I. confirming and correlating all quantities
II. selecting fabrication processes
III. coordinating the work with that of other trades
IV. general conformance with design concept
V. markings as noted

AnswerI, II, III are typical exclusions of a shop drawing review. IV is the purpose of the review and V is a response given in the review.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP