Sanitary drainage

A building's sanitary drainage system continues from the house (building) drain to the house (building) sewer and ultimately to the main sewer line or private disposal system. Where does the house drain end and house sewer begin as commonly designated in local plumbing codes?

A. at exterior envelope of the building
B. at a point 3-5 ft outside the building
C. at a point more than 5 ft outside the building
D. at a point 5 ft inside the property line

AnswerB. at a point 3-5 feet outside of the building. This can vary by municipal ordinance.

ARE 4.0 exam prep: SPD

Comments

Try These Too!

Structural forces

Choose a term that best identifies the type of force shown in this diagram - A. collinear B. concurrent C. nonconcurrent D. noncoplanar

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred