Project vs Construction Costs

Which of the following are included in estimates for both project costs and construction costs?
A. architect design fees
B. FF&E
C. site development
D. financing
E. moving costs
F. labor

AnswerC&F only - the other costs are part of the project costs, but not construction costs.

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Vapor retarders

In this section, a ceiling assembly separates the attic space above from the room interior below. If the building is located in Lewisville, Texas (hot-humid zone), where is the predicted location of condensation and what is the predicted condition of the gypsum board in this assembly? (Select 2 from the following) A. outside face of vapor retarder B. inside face of vapor retarder C. gypsum board will be wet D. gypsum board will be dry