Project vs Construction Costs

Which of the following are included in estimates for both project costs and construction costs?
A. architect design fees
B. FF&E
C. site development
D. financing
E. moving costs
F. labor

AnswerC&F only - the other costs are part of the project costs, but not construction costs.

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP