Which of the following are included in estimates for both project costs and construction costs?
A. architect design fees
B. FF&E
C. site development
D. financing
E. moving costs
F. labor

AnswerC&F only - the other costs are part of the project costs, but not construction costs.

Comments

Try These Too!

Structural forces

Choose a term that best identifies the type of force shown in this diagram - A. collinear B. concurrent C. nonconcurrent D. noncoplanar

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred