Flush panel assembly

Regardless of the way veneers are matched within each panel, which of the following methods of assembling flush panels in a room results in greatest continuity of grain?
A. Sequence matching
B. Warehouse matching
C. Blueprint matching

AnswerC. Blueprint matching - the panels are made to fit the room, aligning with all obstructions (at corners, overlaying doors and cabinetry) without interrupting grain continuity. It is also more expensive than other methods.

ARE 4.0 exam prep: BDCS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD