Skip to main content

Extent of agency

When the contractor's work does not conform to the requirements of the construction documents, the architect has the right to reject it and to require the contractor to remove and replace the non-conforming work. If the contractor fails to rectify or steadily fails to execute work according to the documents, what options are available to the architect?
Answer

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS

Collector walks

Walks next to parking areas where vehicles are able to overhang the walk should be a minimum width. What is this minimum in feet? A. 3 feet B. 4 feet C. 5 feet D. 6 feet Answer These walks should be 6 ft (D.) minimum in width. ARE 4.0 exam prep: SPD