Detailed estimate

Which of the following are indirect costs to be added to a detailed construction cost estimate?
I. Cost escalation contingency amount
II. Permits
III. Labor unit costs
IV. Equipment rental costs

AnswerI, II, IV, but not III. This is considered as part of direct costs, which includes costs per unit of material and labor multiplied by quantities.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Tensegrity

A type of structure whose integrity is derived from the balance between members in tension and in compression is Tensegrity . Compressive components connected by tensile components to other compressive components form a tensegrity structure. What architect-engineer-cosmologist coined this term? Answer

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP