Detailed estimate

Which of the following are indirect costs to be added to a detailed construction cost estimate?
I. Cost escalation contingency amount
II. Permits
III. Labor unit costs
IV. Equipment rental costs

AnswerI, II, IV, but not III. This is considered as part of direct costs, which includes costs per unit of material and labor multiplied by quantities.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Soil Analysis

In sieve analysis, one of the first results measured is the % retained in each sieve of the total sample (W sieve / W total x 100%). If the illustrated sample indicates equal amounts of various sizes of aggregate, where most of the voids in such material will be filled with particles, which gradation term is used? A. Narrow gradation B. Gap gradation C. Dense gradation D. Open gradation E. Rich gradation

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°