Skip to main content

Flood Hazard Mapping

What are two possible options to remove buildings from being located within the level of the 100-year floodplain?


1. raise the building at least 1 foot above the 100-year elevation. 2. select a site for the project that lies entirely outside the 100-yr floodplain.

are-review.blogspot.com

Resource Tip: Consult FEMA's National Flood Insurance Program (NFIP) site for further mapping information and resources.

Comments

Try These Too!

Wood stairs

In wood stair construction, what is the difference between a carriage and a stringer?! Answer A carriage is the principle support for the treads and risers, whereas the stringer is the finish member (face) that treads and risers terminate against. ARE 4.0 exam prep: BDCS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS