Vapor retarders



In this section, a ceiling assembly separates the attic space above from the room interior below. If the building is located in Lewisville, Texas (hot-humid zone), where is the predicted location of condensation and what is the predicted condition of the gypsum board in this assembly? (Select 2 from the following)

A. outside face of vapor retarder
B. inside face of vapor retarder
C. gypsum board will be wet
D. gypsum board will be dry



Answer: A. and C. As Lewisville is a hot-humid location, expect the room interior to be cooled by air-conditioning. Kraft paper facing acts as a vapor retarder with predictable condensation on the outside face, but this is faced on both sides - so the gyp. board will be wet. The vapor retarder should only be located outside of the insulation or between the insulation and the ventilated attic space.

Visit the PPD-PDD page for more study resources!

Reference tip: read a paper about air vs vapor barriers here from conference session E11: Performance of the Building Enclosure of the 2008 Best 1 Conference BEST = Building Enclosure Science & Technology from National Institute of Building Sciences.

Comments

  1. Updated the links to the Building Enclosure paper & NIBS BEST Conferences...

    ReplyDelete

Post a Comment

Try These Too!

Tensegrity

A type of structure whose integrity is derived from the balance between members in tension and in compression is Tensegrity . Compressive components connected by tensile components to other compressive components form a tensegrity structure. What architect-engineer-cosmologist coined this term? Answer

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP

Footing cross-section

When the thickness of a foundation wall = 6", the cross-sectional proportions in this image are appropriate for which of the following: A. a footing supported on clay soil B. light frame construction supporting one floor and one roof C. allowable bearing capacity of foundation soil is low in relation to building loads D. when a continuous footing is required Answer B. light frame construction supporting one floor and one roof (in accordance with Table 1805.4.2) ARE 4.0 exam prep: PPP