Construction type

Fire-resistance rating requirements listed in IBC Table 601 list major building elements based on construction classification. Match these two criteria correctly, choose 2
A. Type IB = roof construction 1 1/2 hrs
B. Type IIB = exterior bearing walls 1 hr
C. Type IIIA = structural frame 1 hr
D. Type VB = floor construction 1 hr
E. Type IVHT = exterior bearing walls 2 hr

AnswerC. and E. are correct. HT = heavy timber.

ARE 4.0 exam prep: BDCS
Reference tip:  Find the online version of Table 601 in this discussion paper here

Comments

  1. Link takes you to a page not found, just thought I let you know.
    Thank you very much for all the useful information.

    ReplyDelete

Post a Comment

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Tensegrity

A type of structure whose integrity is derived from the balance between members in tension and in compression is Tensegrity . Compressive components connected by tensile components to other compressive components form a tensegrity structure. What architect-engineer-cosmologist coined this term? Answer

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP