Skip to main content

Changes in work

During construction, how does the owner unilaterally order changes to the contract without changing its terms?
A by change order document
B by issuing a written order for a minor change
C by construction change directive
D by issuing an addendum
E none of the above



Answer: C. The architect prepares a construction change directive to direct a change in the work prior to an agreement on contract cost and/or time adjustment between the contractor and the owner.

for more ARE5.0 study resources see the CE page

Comments

Try These Too!

Fire evacuation

Which of the following statements best describes why exterior fire escapes are no longer recommended or usually permitted? A. Manufacturing has ceased production of these. B. Rising smoke from lower floors eliminates the safety of using them C. They cannot be securely attached to typical current construction D. They are difficult to maintain Answer B. is the correct answer. Smoke inhalation is as perilous as leaping flames. ARE 4.0 exam prep: BS

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP