Skip to main content

Changes in work

During construction, how does the owner unilaterally order changes to the contract without changing its terms?
A by change order document
B by issuing a written order for a minor change
C by construction change directive
D by issuing an addendum
E none of the above



Answer: C. The architect prepares a construction change directive to direct a change in the work prior to an agreement on contract cost and/or time adjustment between the contractor and the owner.

for more ARE5.0 study resources see the CE page

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Gravity wall

A gravity wall is a type of retaining wall that relies on the force of its own weight to remain upright. As a rule of thumb, gravity walls are suitable for retained heights up to A. 5 feet B. 8 feet C. 10 feet D. 12 feet E. 15 feet Answer C. 10 feet ARE 4.0 exam prep: SPD

Fire zones

The fire zone of a project's site can impact requirements for fire resistive features, certain usage and construction type selection (such as combustible, non-combustible). They are typically designated high hazard, moderate hazard, or low hazard, and mapped geographically. Through which authority are fire zones generally established? Choose 2 A. life safety code B. building code C. local jurisdiction D. state E. NFPA F. FEMA Answer Fire zones are generally established by D. state (state fire code) and through C. local jurisdictions (county or local fire departments) ARE 4.0 exam prep: PPP